Kingman Municipal Airport
Revised On: Mar. 29th, 2024 - 12:24 pm
Revised On: March 29, 2024 - 12:24 p.m.
Location:
- 7000 Flightline Drive, Kingman, Arizona
- 14 acres located on the southwest corner of the Airport
Acceptance Into Voluntary Remediation Program (VRP):
Contaminants of Concern (COCs):
Affected Media:
What are My Health Risks:
For Soil | There is little to no health risk unless there is contact with skin or ingestion of contaminated soil
Site Summary:
- Phase I Site Investigation Report was approved by ADEQ in May 2018.
- Site characterization activities began March 2019 and were completed in October 2019.
- Waste Determination Report submitted March 2021.
- Phase III Work Plan was submitted and approved by ADEQ in November 2021, following a 30-day public comment period. Affected soils will be excavated, removed, and transported to an applicable landfill.
- Soil remediation began August 2023. Work is anticipated to continue through April 2024.