On Feb. 19, 2025, the comment period begins for the work plan for the Pinal Valley Soil Program Voluntary Remediation Program (VRP) site. The comment period ends March 21, 2025.

Notice Details: 

ADEQ has received a work plan and probabilistic risk assessment (PRA) for the Pinal Valley Soil Program VRP site.  The work plan proposes soil investigation and remediation on eligible residential, non-residential, and publicly owned developed properties located in proximity to the Miami Smelter in Miami-Globe, Arizona. These documents were submitted in accordance with Arizona Revised Statutes (A.R.S.) § 49-175 and § 176. 

The Pinal Valley Soil Program VRP site consists of a Study Area defined by Figure 1 in the work plan and located in Miami-Globe, Arizona. The contaminant of concern at the site is arsenic.

Review Documents:

  • Original Published Public Notice | View > 
  • Remedial Action Work Plan | View >
  • Probabilistic Risk Assessment | View >
  • Pinal Valley Soil Program VRP Site Webpage | View >  
  • In person at the ADEQ Record Center | Learn How >

Public Comment Period:

Dates: Feb. 19, 2025 – March 21, 2025

Comments may be submitted as follows:

  •      By Email | Send Email >
  •      By Mail (Must be postmarked or received by March 21, 2025):

ADEQ
Waste Programs Division, Voluntary Remediation Program

Attn: Caitlin Adams
1110 W. Washington St.
Phoenix, AZ  85007