On Oct. 22, 2022, the public comment period begins for the remedial action work plan for EPNG Gila Compressor Station VRP Site in Arlington, Arizona. The comment period ends Nov. 21, 2022.
Public Notice Information
ADEQ has received a work plan for the EPNG Gila Compressor Station VRP site. The work plan proposes optimized groundwater monitored natural attenuation and was submitted in accordance with Arizona Revised Statutes (A.R.S.) § 49-175 and § 176.
Site
The EPNG Gila Compressor Station VRP Site
Near S Old US Highway 80 and Agua Caliente Road
The EPNG Gila Compressor Station VRP site consists of approximately 151 acres formerly used to compress natural gas located in Arlington, Arizona. Contaminants of concern at the site are metals | Learn More >
Review Documents
Original Published Public Notice | View/Download >
Groundwater Remedial Action Work Plan | View/Download >
You may also review the documentation at the ADEQ Record Center | Learn How >
Public Comment Period
Dates: Oct. 22, 2022 – Nov. 21, 2022
Comments may be submitted as follows:
By Email | Send Email >
By Mail (Must be postmarked or received by Nov. 21, 2022):
ADEQ
Nichole Osuch
Waste Programs Division
1110 W. Washington St.
Phoenix, AZ 85007