Skip to main content

WPD | VRP | Former Flint Oil Property

VRP Site

Former Flint Oil Property

Revised On: Aug. 12th, 2024 - 12:55 pm

Revised On: Nov. 15, 2023 - 4:00 p.m.

Location: 

  • 500 – 505 West Simpson Street, Tucson, Arizona

Acceptance Into Voluntary Remediation Program (VRP):

  • July 9, 2020

Contaminants of Concern (COCs):

  • Metals (arsenic, cadmium, lead) PAHs and VOCs

Affected Media:

  • Soil

What are My Health Risks:

For Soil | There is little to no health risk unless there is contact with skin or ingestion of contaminated soil.

Site Summary:

  • July 9, 2020, the Application was accepted into the VRP
  • In August 2022, Former Flint Oil Property submitted a Site Characterization Report (SCR)
  • In September 2022, ADEQ provided a review of the SCR and requested additional clarifications
  • The Volunteer submitted a Sampling and Analysis Plan (SAP) on June 23, 2023
  • VRP requested revisions to the SAP on Sept 12, 2023
  • The Volunteer submitted a Revised Work Plan and SAP on March 20, 2024
  • The VRP issued a Preliminary Approved the Work Plan and SAP on July 31, 2024
  • The Work Plan and SAP are in Public Notice | View Notice >

Project Manager
P: 602-771-2256
Email >


VRP Unit Manager
P: 602-771-1612
Email >