VRP Site

Bisbee Smelter Town Cleanup Phase II

Revised On: Oct. 17th, 2024 - 03:14 pm

Location: 

  • Bisbee, Arizona

Acceptance Into Voluntary Remediation Program (VRP):

  • Feb. 10, 2023

Contaminants of Concern (COCs):

  • Metals from historic mine smelter emissions

Affected Media:

  • Soil

What are My Health Risks:

For Soil | There is little to no health risk unless there is contact with skin or ingestion of contaminated soil

Site Summary:

  • Town cleanup from historic smelter emissions
  • Volunteer is conducting ongoing Community Outreach activities in the city
  • Volunteer submitted a Sampling and Analysis Plan (SAP) and Quality Assurance Project Plan (QAPP) on Jan. 23, 2024
  • The VRP approved the SAP and QAPP on March 26, 2024
  • Volunteer submitted a Remedial Action Work Plan (RAWP) on Aug. 7, 2024
  • The VRP preliminarily approved the RAWP on Aug. 22, 2024
  • The RAWP was available for public comment Sept. 4, 2024 – Oct. 4, 2024
  • The VRP issued Final Approval of the RAWP on Oct. 8, 2024