Engineering Review | Drinking Water Facilities Review Fees
Fees are calculated on a per-unit basis (i.e., a separate fee is assessed for each separate storage tank, booster pump, disinfection device or main line extension), and fees for each application type are cumulative so the applicant must pay the total of all pertinent fees.
Approval to Construct for a Public Water Distribution System
150 or fewer service connections | $900
151 to 300 service connections | $1,400
301 to 450 service connections | $1,900
451 to 600 service connections | $2,400
601 to 750 service connections | $2,900
Each additional 150 service connections | Add $500
Water Treatment Plants and Blending Plans (including new source approval, if applicable)
< 0.1 million gallons per day | $1,500
≥ 0.1 and < 1 million gallons per day | $2,000
≥ 1 and < 5 million gallons per day | $3,000
≥ 5 million gallons per day | $5,000
Well (including new source approval, if applicable)
$1,250
Storage Tank
$800
Booster Pump
$800
Main Line Extension
$250
Chlorinators/Disinfection Devices
$250 each
Extension of Time to Construct1
50% of the application fee (not to exceed $500)
Priority Review Fee2
Double the standard fee
1Extensions of time to construct are issued pursuant to Arizona Administrative Code R18-5-505(E). The Section states than an Approval to Construct becomes void if construction is not commenced within a specific time period, unless ADEQ grants an extension of time.
2Priority Review projects require ADEQ authorization prior to filing.